Chleansaid Wind Farm - Construction Timeline

 

Our Timeline

December 2023

- Section 36 Planning Application consented by the Scottish Government

Autumn 2026

- Site set-up, A836 works, borrow pits and initial access works

Spring/Summer 2027

- Access tracks and turbine foundations

- Substation and electrical works

2028

- Turbine component deliveries and erection

- Energisation and commissioning, with commercial operation expected towards the end of the year